Example

Consider a print run of 3000 shirts which requires Boxing and despatching on the same day.

Print run rate is 500 per hour; boxing up and labelling can be also done at 500 per hour.

This means there the total processing time is 12 hrs – 6hrs to print and 6 hrs to box and label.

If printing starts at 11a.m the timeline looks like this

 

 

Boxing and labelling Once Printing Complete

Printing

Boxing Up / Labelling

11:00 AM

12:00 PM

1:00 PM

2:00 PM

3:00 PM

4:00 PM

5:00 PM

6:00 PM

7:00 PM

8:00 PM

9:00 PM

10:00 PM

11:00 PM

 

 

 

 

 

 

 

 

 

 

 

 

 

 

However, if boxing and labelling were done as the print run is underway – i.e., doing these tasks in parallel, the timel ine would look something like this.

 

Boxing Up / Labelling

Printing

 

11:00 AM

12:00 PM

1:00 PM

2:00 PM

3:00 PM

4:00 PM

5:00 PM

6:00 PM

 

 

 

 

 

 

 

 

 

It is the same total hours to process the job, but the completion time is brought forward by 5hrs.

Additionally, by boxing at the point of production, the number of times garments are handled is reduced (e.g. rather than (1) place items on a trolley only to (2) remove them later and then (3) Pick and (4) Boxed – if they are boxed at source, then fewer actions are needed)

 

Now that you understand the reasoning for this – let’s look at the process of how to do this and record the activity in strokeone.