Embroidery Pre Run Checks

The embroiderer should refer to the Tech Spec from the TOT computer system located on the Desktop Computer or IPad.

1. Do the colours match the visual?

2. Does the visual reflect design correctly?

3. Have you been given correct garments?

4. Is this a repeat or, brand new job?

5. If new job, a new sample has to be created and passed to the Manager for checking

6. Locate and insert the DST file into machine

7. If existing job, refer sample card to embroidery machine screen and load appropriate thread colours

8. Establish size of design and use appropriate frame for framing the garments and establish which canvas is required

9. Load the garment onto the frame and establish which bobbin is required?

10. Confirm which needles are required?

11. Load the garments on the machine and establish starting point

12. During first run check all heads that correct design and colours are in correct sequence. Refer to sample card if required

13. After first run DOES IT LOOK RIGHT

14. If you are unhappy with any of the final products or any part of the process, immediately refer your concerns to your Manager